Feasibility studies for two campuses in Zaragoza (PTR and Villanueva de Gállego) of up to 400MW each. They include urban due diligence, fibre connection, energy availability and preliminary land and environmental studies
- Built area: 970,274 m2
- Power: 900 MW
Hired services:
- Due diligence (urban planning, environmental, energy, fibre availability)
- Preliminary analyses: CAPEX analysis, HV line deviation study
- Initial studies: Geotechnical campaign, soil contamination studies, environmental corrosion study, environmental dust analysis, topographical study