Design engineering of a 90 MVA 30/220 kV Los Galeazos substation in Sevilla
Preparation of technical administrative documentation for the construction of a 90 MVA 30/220 kV Los Galeazos substation. The project included:
- Environmental impact study
- Engineering of protection, control, communications, civil, structural, hydrology, drainage, topography and geotechnical engineering
- Burying of 220 kV line to REE substation
SPAIN
Hired services:
- Administrative projects for AAC processing
- Study of alternatives for evacuation of photovoltaic plant
- Environmental impact study for substation, photovoltaic plant and underground high voltage line.